Pace Digitek Secures ₹2,691 Crore NTPC Green Energy BESS Order

0
35

Pace Digitek has secured a Letter of Award (LoA) worth ₹2,691 crore, including GST, from NTPC Green Energy Limited for a 600 MW/1,800 MWh Battery Energy Storage System (BESS) project in Gujarat. The contract covers engineering, procurement and construction (EPC), along with long-term operations and maintenance of the project.

The company stated that this is its largest BESS contract to date, with project completion scheduled by September 2027. The project will be developed at the NTPC REL Khavda Solar Plant in Gujarat under Cluster-01 of the larger 3,300 MWh battery energy storage project.

The scope of work includes BESS system supply, system integration, installation, testing, commissioning and civil works, along with 15 years of operations and maintenance (O&M). The awarded capacity is divided into two blocks, with Block-01 comprising 300 MW/900 MWh and Block-02 comprising 300 MW/900 MWh.

Following the latest contract, Pace Digitek’s cumulative order inflows for FY2026-27 have reached ₹5,129 crore, while its total executable order book stands at ₹13,427 crore. The company’s consolidated BESS project portfolio has also increased to 6.62 GWh across Engineering, Procurement and Construction (EPC), Build-Own-Operate (BOO) and Build-Own-Operate-Transfer (BOOT) models.

Pace Digitek attributed its success in securing the contract partly to its compliance with the Class-I Local Supplier criteria, which require a minimum of 50% local content in the value of goods, services and works. The company currently has 5 GWh of operational domestic BESS manufacturing capacity, supported by an in-house container fabrication facility. It is also progressing with plans to expand its manufacturing capacity to 10 GWh to address growing demand for energy storage solutions.

Commenting on the development, Venugopalrao Maddisetty, Chairman and Managing Director of Pace Digitek Limited, said the order reflects the company’s manufacturing scale, engineering capabilities and project execution experience. He also highlighted the importance of domestic manufacturing and local content in supporting India’s energy storage ambitions. The company will continue focusing on manufacturing expansion, project execution and maintaining a balanced portfolio of BESS supply, EPC and long-term projects.